Title: Developing a fuzzy risk assessment model for guaranteed maximum price and target cost contracts in South Australia
Authors: Chan, DWM 
Chan, JHL
Ma, T
Issue Date: Aug-2014
Source: Facilities, Aug. 2014, v. 32, no. 11/12, p. 624-646
Abstract: Purpose – This paper aims to develop a fuzzy risk assessment model for construction projects procured with target cost contracts and guaranteed maximum price contracts (TCC/GMP) using the fuzzy synthetic evaluation method, based on an empirical questionnaire survey with relevant industrial practitioners in South Australia.
Design/methodology/approach – A total of 34 major risk factors inherent with TCC/GMP contracts were identified through an extensive literature review and a series of structured interviews. A questionnaire survey was then launched to solicit the opinions of industrial practitioners on risk assessment of such risk factors.
Findings – The most important 14 key risk factors after the computation of normalised values were selected for undertaking fuzzy evaluation analysis. Five key risk groups (KRGs) were then generated in descending order of importance as: physical risks, lack of experience of contracting parties throughout TCC/GMP procurement process, design risks, contractual risks and delayed payment on contracts. These survey findings also revealed that physical risks may be the major hurdle to the success of TCC/GMP projects in South Australia.
Practical implications – Although the fuzzy risk assessment model was developed for those new-build construction projects procured by TCC/GMP contracts in this paper, the same research methodology may be applied to other contracts within the wide spectrum of facilities management or building maintenance services under the target cost-based model. Therefore, the contribution from this paper could be extended to the discipline of facilities management as well.
Originality/value – An overall risk index associated with TCC/GMP construction projects and the risk indices of individual KRGs can be generated from the model for reference. An objective and a holistic assessment can be achieved. The model has provided a solid platform to measure, evaluate and reduce the risk levels of TCC/GMP projects based on objective evidence instead of subjective judgements. The research methodology could be replicated in other countries or regions to produce similar models for international comparisons, and the assessment of risk levels for different types of TCC/GMP projects (including new-build or maintenance) worldwide.
Keywords: Risk management
Fuzzy synthetic evaluation
Guaranteed maximum price contracts
South Australia
Target cost contracts
Publisher: Emerald Group Publishing Limited
Journal: Facilities 
ISSN: 0263-2772
EISSN: 1758-7131
DOI: 10.1108/F-08-2012-0063
Rights: © Emerald Group Publishing Limited
This article is (c) Emerald Group Publishing and permission has been granted for this version to appear here (http://repository.lib.polyu.edu.hk/). Emerald does not grant permission for this article to be further copied/distributed or hosted elsewhere without the express permission from Emerald Group Publishing Limited.
The published version is available at http://dx.doi.org/10.1108/F-08-2012-0063
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
PolyU IR Submission 2014_FJ_1.pdfPre-published version250.74 kBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

219
Last Week
0
Last month
Citations as of Mar 24, 2024

Downloads

291
Citations as of Mar 24, 2024

SCOPUSTM   
Citations

13
Last Week
0
Last month
0
Citations as of Mar 28, 2024

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.