Title: A further study on two-agent parallel-batch scheduling with release dates and deteriorating jobs to minimize the makespan
Authors: Gao, Y
Yuan, J
Ng, CT 
Cheng, TCE 
Issue Date: 16-Feb-2019
Source: European journal of operational research, 16 Feb. 2019, v. 273, no. 1, p. 74-81
Abstract: We re-visit the two-agent scheduling on a parallel-batch machine to minimize makespan, where jobs have release dates and linear deteriorating processing times. The objective is to minimize the makespan of agent A with the makespan of agent B being bounded. In the paper Tang, Zhao, Liu, and Leung (2017), the authors reported comprehensive research for this scheduling model. Especially, they presented polynomial-time algorithms for the following four problems. In the first, the batch capacity is unbounded and the two agents are compatible. In the second, the batch capacity is bounded, the two agents are incompatible, the A-jobs have a fixed number of normal processing times, and the B-jobs have a common release date. In the third and forth, the batch capacity is bounded, the two agents are compatible, and the release dates and normal processing times are either agreeable or reversely agreeable. But their discussions for the above four problems are logically confusing. In this paper we present a more efficient polynomial-time algorithm for the first problem and show that the other three problems are NP-hard. We also present a pseudo-polynomial-time algorithm for the version where the batch capacity is bounded, the two agents are incompatible, and A-jobs and B-jobs have their common release dates, respectively. We finally present a strongly polynomial-time algorithm for the version where the batch capacity is unbounded and the two agents are incompatible.
Keywords: Deterioration
Parallel-batch
Release dates
Two agents
Publisher: Elsevier
Journal: European journal of operational research 
ISSN: 0377-2217
EISSN: 1872-6860
DOI: 10.1016/j.ejor.2018.07.040
Rights: © 2018 Elsevier B.V. All rights reserved.
© 2018. This manuscript version is made available under the CC-BY-NC-ND 4.0 license https://creativecommons.org/licenses/by-nc-nd/4.0/.
The following publication Gao, Y., Yuan, J., Ng, C. T., & Cheng, T. C. E. (2019). A further study on two-agent parallel-batch scheduling with release dates and deteriorating jobs to minimize the makespan. European Journal of Operational Research, 273(1), 74-81 is available at https://doi.org/10.1016/j.ejor.2018.07.040.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Ng_Further_Study_Two-Agent.pdfPre-Published version837.16 kBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

81
Citations as of Apr 14, 2025

Downloads

63
Citations as of Apr 14, 2025

SCOPUSTM   
Citations

32
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

24
Citations as of Oct 10, 2024

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.