Title: Exploring the critical production risk factors for modular integrated construction projects
Authors: Wuni, IY 
Shen, GQ 
Issue Date: 11-Jan-2023
Source: Journal of facilities management, 11 Jan. 2023, v. 21, no. 1, p. 50-68
Abstract: Purpose: The factory production stage constitutes the bridge in the supply chains of modular integrated construction (MiC) projects. It embodies the fundamental differences between MiC and site-based construction. However, there is a poverty of knowledge of the uncertainties and risk events at the production stage. This study aims to investigate the critical production risk factors (PRFs) for MiC projects.
Design/methodology/approach: Comprehensive literature research and expert review identified and validated 22 candidate PRFs for MiC projects. A structured questionnaire survey was then used to gather opinions of domain experts in 18 countries on the relative impact of the validated PRFs for MiC projects. The collected data were analysed using multiple statistical techniques.
Findings: Statistical analysis identified nine critical PRFs for MiC projects. The top five include dimensional conflicts between modules during production; delays in production materials procurement; defective design; design information gap between designer and manufacturer; and limited capacity of manufacturers.
Originality/value: The study addressed the gap associated with identifying critical risk factors peculiar to the factory production stage of MiC projects. Its novelty lies in providing an opposite assessment of severities and prioritization of critical PRFs for MiC projects. The prioritized critical PRFs for MiC projects may inform resource allocation. Thus, it provides valuable information to MiC production specialists and project managers in their production risk planning and management strategies. The identified PRFs contribute to the theoretical checklist of MiC supply chain risk factors and may assist practitioners in assessing the severity levels of the PRFs of their MiC projects.
Keywords: Modular integrated construction
Production risks
Risk factors
Risk management
Severity
Supply chain
Publisher: Emerald Group Publishing Limited
Journal: Journal of facilities management 
ISSN: 1472-5967
EISSN: 1741-0983
DOI: 10.1108/JFM-03-2021-0029
Rights: © Emerald Group Publishing Limited. This AAM is provided for your own personal use only. It may not be used for resale, reprinting, systematic distribution, emailing, or for any other commercial purpose without the permission of the publisher.
The following publication Wuni, I.Y. and Shen, G.Q. (2023), "Exploring the critical production risk factors for modular integrated construction projects", Journal of Facilities Management, Vol. 21 No. 1, pp. 50-68 is published by Emerald and is available at https://doi.org/10.1108/JFM-03-2021-0029.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Wuni_Exploring_Critical_Production.pdfPre-Published version1.43 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

199
Last Week
6
Last month
Citations as of Nov 30, 2025

Downloads

215
Citations as of Nov 30, 2025

SCOPUSTM   
Citations

18
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

16
Citations as of Dec 18, 2025

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.