Title: | Factors affecting schedule delay, cost overrun, and quality level in public construction projects | Authors: | Larsen, JK Shen, GQP Lindhard, SM Brunoe, TD |
Issue Date: | Jan-2016 | Source: | Journal of management in engineering, Jan. 2016, v. 32, no. 1, 4015032, p.1-10 | Abstract: | As a result of the loss of financial resources and the need to optimize projects, academics, politicians, and the construction industry have become increasingly aware of the challenges presented by the frequent time and cost overruns and reduced quality of construction projects. The purpose of this study was to analyze the factors that project managers experience as having the greatest effect on time, cost, and quality, and to discover whether the effects of these factors are significantly different from each other. A questionnaire with 26 factors identified from interviews was sent to the full population of publicly employed project managers. Factors were ranked using the relative importance index and tested for significant differences using Friedman's test. Wilcoxon's test was used in a post-hoc analysis. From the findings it was determined that the most influential factor for time is unsettled or lack of project funding; for cost, errors or omissions in consultant material; and for quality, errors or omissions in construction work. The main conclusion of this research is that project schedule, budget, and quality level are affected in significantly different ways. Therefore, a project manager cannot handle such critical issues by focusing only on schedule or budget complications; nor can he or she assume that time, cost, and quality are equally affected. | Keywords: | Construction management Cost overrun Denmark Quality level Schedule delay |
Publisher: | American Society of Civil Engineers | Journal: | Journal of management in engineering | ISSN: | 0742-597X | EISSN: | 1943-5479 | DOI: | 10.1061/(ASCE)ME.1943-5479.0000391 | Rights: | © 2015 American Society of Civil Engineers The following publication Larsen, J. K., Shen, G. Q., Lindhard, S. M., & Brunoe, T. D. (2015). Factors affecting schedule delay, cost overrun, and quality level in public construction projects. Journal of management in engineering, 32(1), 04015032 is available at http://dx.doi.org/10.1061/(ASCE)ME.1943-5479.0000391 |
Appears in Collections: | Journal/Magazine Article |
Files in This Item:
File | Description | Size | Format | |
---|---|---|---|---|
Larsen_Jesper_Kranker_2015.pdf | Pre-Published version | 830.3 kB | Adobe PDF | View/Open |
Page views
1,634
Last Week
21
21
Last month
Citations as of Apr 14, 2025
Downloads
7,506
Citations as of Apr 14, 2025
SCOPUSTM
Citations
261
Last Week
0
0
Last month
Citations as of Aug 15, 2024
WEB OF SCIENCETM
Citations
221
Last Week
1
1
Last month
Citations as of May 8, 2025

Google ScholarTM
Check
Altmetric
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.