Please use this identifier to cite or link to this item:
http://hdl.handle.net/10397/2368
Title: | Achieving better performance through target cost contracts - The tale of an underground railway station modification project | Authors: | Chan, DWM Lam, TIP Chan, APC Wong, JMW |
Issue Date: | Apr-2010 | Source: | Facilities, 2010, v. 28, no. 5/6, p. 261-277 | Abstract: | Purpose – This paper aims to explore the implementation framework, project performance, underlying motives, perceived benefits, potential difficulties, as well as critical success factors, of adopting the target cost contracting (TCC) form of procurement, based on an in-depth real-life case study of a challenging underground railway station modification project in Hong Kong. Design/methodology/approach – The case project was analysed by means of the related project documentation and face-to-face interviews with the relevant senior representatives from the client organisation. Findings – The target cost-based procurement strategy generates a plethora of benefits throughout the whole delivery process of the project case, including the provision of cost incentives for the contractor to work efficiently, aligning individual goals of various contracting parties with the overall project objectives, achieving better value for money and more satisfactory overall project performance in terms of time, cost and dispute occurrence. Practical implications – Although the selected TCC case study project is based in Hong Kong, the research findings and hands-on experience of the relevant industrial practitioners may be cross-referenced to other similar TCC projects in other parts of the world for international comparisons. Originality/value – The paper provides some useful insights into assisting key project stakeholders in maximising the benefits, whilst minimising the detriments brought about by potential difficulties in launching the TCC scheme. It seeks more research evidence to evaluate the entire project delivery process, and capture the levels of success and lessons learned from previous TCC construction projects for generating best practice recommendations to achieve better construction performance. |
Keywords: | Target cost contracting Procurement strategies Gain-share/pain-share arrangement Performance measurement Case study Hong Kong |
Publisher: | Emerald Group Publishing Limited | Journal: | Facilities | ISSN: | 0263-2772 | EISSN: | 1758-7131 | DOI: | 10.1108/02632771011031501 | Rights: | Facilities © 2010 Emerald Group Publishing Limited. |
Appears in Collections: | Journal/Magazine Article |
Files in This Item:
File | Description | Size | Format | |
---|---|---|---|---|
PolyU IR Submission 2010_FJ_2.pdf | Pre-published version | 192 kB | Adobe PDF | View/Open |
Page views
294
Last Week
0
0
Last month
Citations as of Apr 14, 2025
Downloads
892
Citations as of Apr 14, 2025
SCOPUSTM
Citations
32
Last Week
0
0
Last month
0
0
Citations as of Apr 24, 2025

Google ScholarTM
Check
Altmetric
Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.