Title: Data-driven out-of-order model for synchronized planning, scheduling, and execution in modular construction fit-out management
Authors: Jiang, Y
Li, M
Ma, BJ
Zhong, RY
Huang, GQ 
Issue Date: 15-Aug-2024
Source: Computer-aided civil and infrastructure engineering, 15 Aug. 2024, v. 39, no. 16, p. 2457-2480
Abstract: Fit-out operations in modular construction exhibit unique features, such as limited room space and diversely distributed operations in the building. These features pose significant challenges to planning, scheduling, and execution (PSE) of fit-out activities due to operational parallelism, distributional diversity, and narrower constrained time window in modular construction. Hence, logistics-operation and multi-operations synchronizations in a real-time manner are crucial for PSE of modular construction fit-out management. With the support of cutting-edge information technologies, the real-time data inside the generated digital twins can simplify online optimization models and convert stochastic factors into deterministic parameters. This paper formulates a novel real-time data-driven Out-of-Order (OoO) model for synchronized PSE in modular construction fit-out management. Drawing inspiration from OoO mechanism in Central Processing Unit (CPU), a real-time data-driven and rolling-horizon-based OoO model is proposed for PSE of modular construction fit-out, employing a forward heuristic algorithm for solution. Time–space–state data from digital twins are updated to facilitate dynamic decision-making of managers. Through stochastic computational experiments, we demonstrate the effectiveness of OoO model in optimizing project metrics and the improved resilience in uncertain environments.
Publisher: Wiley-Blackwell Publishing, Inc.
Journal: Computer-aided civil and infrastructure engineering 
ISSN: 1093-9687
EISSN: 1467-8667
DOI: 10.1111/mice.13203
Rights: This is an open access article under the terms of the Creative Commons Attribution License (http://creativecommons.org/licenses/by/4.0/), which permits use, distribution and reproduction in any medium, provided the original work is properly cited.
© 2024 The Authors. Computer-Aided Civil and Infrastructure Engineering published by Wiley Periodicals LLC on behalf of Editor.
The following publication Jiang, Y., Li, M., Ma, B. J., Zhong, R. Y., & Huang, G. Q. (2024). Data-driven out-of-order model for synchronized planning, scheduling, and execution in modular construction fit-out management. Computer-Aided Civil and Infrastructure Engineering, 39, 2457–2480 is available at https://doi.org/10.1111/mice.13203.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Jiang_Data‐driven_Out‐of‐order_Model.pdf2.35 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Version of Record
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

19
Citations as of Apr 14, 2025

Downloads

9
Citations as of Apr 14, 2025

SCOPUSTM   
Citations

6
Citations as of Sep 12, 2025

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.