Title: Schedule delay analysis of prefabricated housing production : a hybrid dynamic approach
Authors: Li, CZ
Hong, J
Fan, C
Xu, X
Shen, GQ 
Issue Date: 10-Sep-2018
Source: Journal of cleaner production, 10 Sept 2018, v. 195, p. 1533-1545
Abstract: Design, manufacturing, storage, transportation, and on-site assembly are fundamental processes in prefabricated housing production (PHP) in Hong Kong. However, these processes are fragmented and entail various risks that adversely affect the schedule performance of PHP, thereby causing frequent delay problems in PHP projects and hindering the government from satisfying the high housing demands. Accordingly, many researchers have examined these schedule risks to resolve these delay problems. However, none of these studies developed an effective tool for managing schedule risks of PHP by envisaging the key characteristics of schedule risks and PHP. Most of previous research regarding to the management of prefabrication construction tends to consider risks from static and isolated perspectives, despite that these risks are coherently interrelated with each other and their influence varies throughout the whole PHP process. To fill the research gaps, a hybrid dynamic model is developed in this research to evaluate and simulate the impact of identified schedule risks on the schedule performance of PHP in view of underlying interrelationships and interactions, employing the hybrid system dynamics (SD) and discrete event simulation (DES) method. The resulting hybrid model is validated through a serial of model structure tests and model behavior tests, with the use of data collected from a PHP project in Hong Kong. This study offers an in-depth understanding of how schedule performance of PHP are dynamically influenced by interrelationships and interactions underlying various schedule risk variables. The developed model not only has the benefits of ease of modifying model structure to reflect real schedule situation of PHP project, performing various risk analyses and communicating with simulation results, but also is of value of providing an experiment platform for identifying and determining managerial and technical solutions proposed to minimize and mitigate the influence of corresponding schedule risks prior to implementation.
Keywords: Discrete event simulation
Hong Kong
Prefabricated housing production
Risk
Schedule delay
System dynamics
Publisher: Elsevier BV
Journal: Journal of cleaner production 
ISSN: 0959-6526
DOI: 10.1016/j.jclepro.2017.09.066
Rights: © 2017 Elsevier Ltd. All rights reserved.
© 2017. This manuscript version is made available under the CC-BY-NC-ND 4.0 license https://creativecommons.org/licenses/by-nc-nd/4.0/
The following publication Li, C. Z., Hong, J., Fan, C., Xu, X., & Shen, G. Q. (2018). Schedule delay analysis of prefabricated housing production: A hybrid dynamic approach. Journal of cleaner production, 195, 1533-1545 is available at https://doi.org/10.1016/j.jclepro.2017.09.066.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Shen_Schedule_Delay_Analysis.pdfPre-Published version5.16 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

110
Last Week
2
Last month
Citations as of Nov 30, 2025

Downloads

246
Citations as of Nov 30, 2025

SCOPUSTM   
Citations

70
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

63
Citations as of Dec 18, 2025

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.