Title: Early-stage cost estimation model for power generation project with limited historical data
Authors: Lee, JG
Lee, HS
Park, M
Seo, J 
Issue Date: 2022
Source: Engineering, construction and architectural management, 2022, v. 29, no. 7, p. 2599-2614
Abstract: Purpose: Reliable conceptual cost estimation of large-scale construction projects is critical for successful project planning and execution. For addressing the limited data availability in conceptual cost estimation, this study proposes an enhanced ANN-based cost estimating model that incorporates artificial neural networks, ensemble modeling and a factor analysis approach.
Design/methodology/approach: In the ANN-based conceptual cost estimating model, the ensemble modeling component enhances training, and thus, improves its predictive accuracy and stability when project data quantity is low; and the factor analysis component finds the optimal input for an estimating model, rendering explanations of project data more descriptive.
Findings: On the basis of the results of experiments, it can be concluded that ensemble modeling and FAMD (Factor Analysis of Mixed Data) are both conjointly capable of improving the accuracy of conceptual cost estimates. The ANN model version combining bootstrap aggregation and FAMD improved estimation accuracy and reliability despite these very low project sample sizes. Research limitations/implications: The generalizability of the findings is hard to justify since it is difficult to collect cost data of construction projects comprehensively. But this difficulty means that our proposed approaches and findings can provide more accurate and stable conceptual cost forecasting in the early stages of project development.
Originality/value: From the perspective of this research, previous uses of past-project data can be deemed to have underutilized that information, and this study has highlighted that — even when limited in quantity — past-project data can and should be utilized effectively in the generation of conceptual cost estimates.
Keywords: Construction planning
Estimating
Project management
Publisher: Emerald Group Publishing Limited
Journal: Engineering, construction and architectural management 
ISSN: 0969-9988
EISSN: 1365-232X
DOI: 10.1108/ECAM-04-2020-0261
Rights: © Emerald Publishing Limited. This AAM is provided for your own personal use only. It may not be used for resale, reprinting, systematic distribution, emailing, or for any other commercial purpose without the permission of the publisher.
The following publication Lee, J.G., Lee, H.-S., Park, M. and Seo, J. (2022), "Early-stage cost estimation model for power generation project with limited historical data", Engineering, Construction and Architectural Management, Vol. 29 No. 7, pp. 2599-2614 is published by Emerald and is available at https://dx.doi.org/10.1108/ECAM-04-2020-0261
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Seo_Early-Stage_Cost_Estimation.pdfPre-Published version1.18 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

139
Last Week
9
Last month
Citations as of Nov 30, 2025

Downloads

347
Citations as of Nov 30, 2025

SCOPUSTM   
Citations

15
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

9
Citations as of Dec 18, 2025

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.