Title: Factors affecting delays in rail transportation projects using Analytic Network Process : the case of Iran
Authors: Tavassolirizi, M
Sarvari, H
Chan, DWM 
Olawumi, TO 
Issue Date: 2022
Source: International journal of construction management, 2022, v. 22, no. 14, p. 2712-2723
Abstract: Delays in the implementation and commissioning of rail transportation projects can cause economic damages to project stakeholders and the cities linked by such rail networks. Hence, the current study aims to investigate the key delay factors and provides salient recommendations. In this study, multi-criteria decision-making–the Analytic Network Process (ANP) and the DEMATEL (Decision Making trial and evaluation laboratory) method was employed to help decision-makers in prioritizing these delay factors and evaluating their interactions, respectively. A Delphi approach was used to validate the study’s findings via expert questionnaire surveys–based on a rail transportation development project for the Mobarakeh Steel Complex (MSC). The study’s findings revealed the management factors as the most important delay factors, followed closely by the financial, design, and implementation factors. Other potent issues include the existence of numerous decision-making stations, lack of central role, and sufficient authority for the project managers are responsible for project delays. Overall, the results show that resolving problems with the ‘management’ domain can significantly avoid or alleviate the extent of delays in rail transportation development projects. The study’s findings and recommendations can serve as a policy and consultative instrument for the relevant stakeholders in the railway industry.
Keywords: Analytic Network Process (ANP)
DEMATEL
Iran
Project delays
Rail transportation project
Publisher: Taylor & Francis
Journal: International journal of construction management 
ISSN: 1562-3599
EISSN: 2331-2327
DOI: 10.1080/15623599.2020.1819946
Rights: © 2020 Informa UK Limited, trading as Taylor & Francis Group
This is an Accepted Manuscript of an article published by Taylor & Francis in International Journal of Construction Management on 21 Sep 2020 (published online), available at: http://www.tandfonline.com/10.1080/15623599.2020.1819946
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Tavassoli_Delays_Rail_Transportation.pdfPre-Published version1.49 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

95
Last Week
0
Last month
Citations as of Apr 14, 2025

Downloads

169
Citations as of Apr 14, 2025

SCOPUSTM   
Citations

24
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

16
Citations as of Oct 10, 2024

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.