Title: Defining work-zones for resource allocation in Hong Kong public housing project construction using heuristic rules and operations simulation
Authors: Lin, Z 
Siu, F 
Chan, D 
Lau, D
Issue Date: 2021
Source: Journal of information technology in construction, 2021, v. 26, p. 657-680
Abstract: In Hong Kong, 6-day construction cycle always being used for constructing one typical floor of concrete building superstructure in a week. Work-zones are defined in the working platform for better allocation of limited resources. Once the work-zones are defined, the resources (labour, plant, materials) will be allocated to a specific zone to deliver the works on a particular day of the 6-day construction cycle. In practice, the definition of work-zone is dependent on the experience of project manager. Yet, there is no past research studied the evaluation of work-zone definition schemes. As such, in this research study, three heuristic rules are proposed for choosing better scheme of work-zone. The heuristic rules are based on (i) lengths of work-zone dividing line, (ii) fluctuations of daily duration, and (iii) utilisation rates of resource. To illustrate the steps of evaluating the scheme, an illustrative example is given. To illustrate the method application of the rules, a practical case study of constructing a 40-storey housing is given. The proposed rules were verified based on sensitivity analysis and expert validation. Conclusions are drawn by expressing the contributions and limitations of the proposed rules, followed by suggesting future research works.
Keywords: 6-day cycle
Productivity
Simulation
Work content
Work zone
Publisher: International Council for Research and Innovation in Building and Construction
Journal: Journal of information technology in construction 
EISSN: 1874-4753
DOI: 10.36680/j.itcon.2021.035
Rights: © 2021 The author(s). This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited
The following publication Lin Z, Siu F, Chan D, Lau D (2021). Defining work-zones for resource allocation in Hong Kong public housing project construction using heuristic rules and operations simulation, ITcon Vol. 26, Special issue CIB World Building Congress 2019: Information technology of smart city development, pg. 657-680, https://doi.org/10.36680/j.itcon.2021.035 is available at https://dx.doi.org/10.36680/j.itcon.2021.035.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
2021_35-ITcon-Lin.pdf818.53 kBAdobe PDFView/Open
Open Access Information
Status open access
File Version Version of Record
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

77
Last Week
1
Last month
Citations as of May 5, 2024

Downloads

31
Citations as of May 5, 2024

SCOPUSTM   
Citations

1
Citations as of Apr 26, 2024

WEB OF SCIENCETM
Citations

1
Citations as of Feb 29, 2024

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.