Title: Optimal work pattern for construction workers in hot weather : a case study in Hong Kong
Authors: Yi, W 
Chan, APC 
Issue Date: 8-Jul-2014
Source: Journal of computing in civil engineering, 10.1061/(ASCE)CP.1943-5487.0000419, 05014009
Abstract: Having established a Monte Carlo simulation-based algorithm to optimize work–rest schedule in a hot and humid environment, this paper attempts to develop the algorithm and identify an optimal work pattern, which may maximize the direct-work rates and minimize the health hazard due to heat stress to the workers concerned. Traditionally, construction workers in Hong Kong start work at 8:00 a.m. and finish work at 6:00 p.m., having one hour lunch break between 12:00 p.m. and 1:00 p.m., and an additional break of 30 min at 3:15 p.m. Construction workers can beat the heat by starting earlier to avoid some extreme conditions, which may occur at certain times of a day. By maintaining the current practice of 9-h working duration for a day, 21 additional work patterns with different start and finish times were proposed and evaluated by the developed optimization algorithm. An optimized schedule (direct-work rate of 87.8%) of working from 7:30 a.m. to 12:00 p.m. with a 20 min break at 9:40 a.m., having lunch break between 12:00 p.m. and 1:00 p.m., and working from 1:00 p.m. to 5:30 p.m. with a 30 min break at 3:00 p.m. is proposed. The proposed work pattern not only maximizes direct-work rates but also minimizes the occurrence of heat stress on construction site. This will enable policy makers to derive solid guidelines for working in hot weather. Because the proposed work pattern is developed specifically for the construction industry, more work is needed to further investigate other industries and other climates to provide a holistic view in the future.
Keywords: Construction industry
Direct-work rates
Hot and humid climate
Monte Carlo simulation
Work patterns
Work–rest schedule
Publisher: American Society of Civil Engineers
Journal: Journal of computing in civil engineering 
ISSN: 0887-3801
EISSN: 1943-5487
DOI: 10.1061/(ASCE)CP.1943-5487.0000419
Rights: © 2014 American Society of Civil Engineers.
This is the author’s version of a work that was accepted for publication in Journal of Computing in Civil Engineering . The article is available at http://dx.doi.org/10.1061/(ASCE)CP.1943-5487.0000419
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Yi_Optimal_Work_Pattern.pdfPre-published version1.49 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

235
Last Week
0
Last month
Citations as of Apr 21, 2024

Downloads

624
Citations as of Apr 21, 2024

SCOPUSTM   
Citations

41
Last Week
0
Last month
0
Citations as of Apr 19, 2024

WEB OF SCIENCETM
Citations

33
Last Week
1
Last month
0
Citations as of Apr 18, 2024

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.