Please use this identifier to cite or link to this item: http://hdl.handle.net/10397/103452
PIRA download icon_1.1View/Download Full Text
Title: Schedule risk modeling in prefabrication housing production
Authors: Li, CZ 
Shen, GQ 
Xu, X
Xue, F 
Sommer, L
Luo, L 
Issue Date: 1-Jun-2017
Source: Journal of cleaner production, 1 June 2017, v. 153, p. 692-706
Abstract: Every country is dealing with its own housing problems; however, none compares with Hong Kong where housing has always been a major concern as a result of low supply over the past decades. Against the constraints in delivering sufficient houses, prefabrication as a sustainable solution for housing has been increasingly advocated for its potential merits of better quality, construction safety and cleaner built environment. However, schedule delay caused by various risks affected the prefabrication housing production (PHP) in Hong Kong. This problem can be further worsened when the manufacturing sector of PHP has entirely moved to offshore areas in the Pearl River Delta region. This study applies system dynamics to recognize and investigate the potential effect of various risks on the scheduling of prefabrication housing construction projects through the employment of Vensim software package. The simulation results show that schedule risks, namely low information interoperability between different enterprise resource planning systems (LIIBDERPS), logistics information inconsistency due to human errors probability (LIIHEP), Delay of delivery of precast element to site (DDPES), and Design information gap between designer and manufacturer (DIGDM) significantly contribute to the schedule delay in PHP. However, schedule is more sensitive toward LIIBDERPS than for the other three risks, indicating that LIIBDERPS should be monitored and given priority. The system dynamic model serves as an effective tool for quantitatively evaluating the effect of various risks on the schedule of PHP, offering valuable references for managers though comparing simulation results under different risk scenarios, so that potential risks that might lead to schedule delay could be identified and handled in advance.
Keywords: Hong Kong
Prefabrication housing production
Schedule risk management
System dynamcis
Publisher: Elsevier BV
Journal: Journal of cleaner production 
ISSN: 0959-6526
DOI: 10.1016/j.jclepro.2016.11.028
Rights: © 2016 Elsevier Ltd. All rights reserved.
© 2016. This manuscript version is made available under the CC-BY-NC-ND 4.0 license https://creativecommons.org/licenses/by-nc-nd/4.0/
The following publication Li, C. Z., Shen, G. Q., Xu, X., Xue, F., Sommer, L., & Luo, L. (2017). Schedule risk modeling in prefabrication housing production. Journal of Cleaner Production, 153, 692-706 is available at https://doi.org/10.1016/j.jclepro.2016.11.028.
Appears in Collections:Journal/Magazine Article

Files in This Item:
File Description SizeFormat 
Shen_Schedule_Risk_Modeling.pdfPre-Published version3.38 MBAdobe PDFView/Open
Open Access Information
Status open access
File Version Final Accepted Manuscript
Access
View full-text via PolyU eLinks SFX Query
Show full item record

Page views

106
Last Week
4
Last month
Citations as of Nov 30, 2025

Downloads

180
Citations as of Nov 30, 2025

SCOPUSTM   
Citations

80
Citations as of Dec 19, 2025

WEB OF SCIENCETM
Citations

75
Citations as of Dec 18, 2025

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.