Title: A fuzzy synthetic evaluation analysis of operational management critical success factors for public-private partnership infrastructure projects
Authors: Osei-Kyei, R 
Chan, APC 
Ameyaw, EE 
Keywords: Critical success factor
Factor analysis
Fuzzy synthetic evaluation model
International survey
Operational management
Public-private partnerships
Issue Date: 2017
Publisher: Emerald Group Publishing Limited
Source: Benchmarking, 2017, v. 24, no. 7, p. 2092-2112 How to cite?
Journal: Benchmarking 
Abstract: Purpose: The purpose of this paper is to identify the factor groupings of a set of 19 critical success factors (CSFs) associated with managing public-private partnership (PPP) projects at the operational stage and examine the most significant factor grouping using fuzzy synthetic evaluation (FSE) technique. Design/methodology/approach: The paper adopted a comprehensive review of the pertinent literature and an empirical questionnaire survey geared towards targeted international PPP experts. Survey responses were analysed using factor analysis and FSE modelling. Findings: The results from factor analysis show five CSF groupings (CSFGs) for managing operational PPPs. These are proficient service delivery and adequate legal structures, simplified payment mechanism and consistent project monitoring, effective contract variations management, suitable stakeholder management mechanism and environmental health and safety control. The FSE modelling shows that “simplified payment mechanism and consistent project monitoring”, is the most critical CSFG. The operational management CSFs under this grouping are acceptable level of user fee charges, efficient and well-structured payment mechanism, consistent project performance monitoring and long-term demand for public facility. Research limitations/implications: The major limitation lies in the low sample size that was used for analysisMergeCell however the years of research and/or industrial experience of respondents and the wide coverage of different cultural backgrounds (18 countries from five regions globally) contribute to the authenticity of the survey responses. Future research should adopt interviews and case study analysis to unravel CSFs in managing operational PPPs. Originality/value: The findings of this study are considerably beneficial to both public authorities and private operators. They inform practitioners of the strategic procedures and measures to employ in optimising the operational performance of PPP projects. Further, the methodology employed allows project management experts to reliably select the operational management CSFs for their projects.
URI: http://hdl.handle.net/10397/74497
ISSN: 1463-5771
EISSN: 1758-4094
DOI: 10.1108/BIJ-07-2016-0111
Appears in Collections:Journal/Magazine Article

Access
View full-text via PolyU eLinks SFX Query
Show full item record

SCOPUSTM   
Citations

4
Last Week
0
Last month
Citations as of Apr 6, 2019

WEB OF SCIENCETM
Citations

1
Last Week
0
Last month
Citations as of Apr 9, 2019

Page view(s)

29
Last Week
0
Last month
Citations as of Apr 16, 2019

Google ScholarTM

Check

Altmetric


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.