Title: Simulation approach to evaluating cost efficiency of selective demolition practices : case of Hong Kong's Kai Tak Airport demolition
Authors: Lu, M
Lau, SC
Poon, CS 
Keywords: Airports and airfields
Case reports
Computer aided simulation
Demolition
Hong Kong
Simulation models
Waste management
Issue Date: 2009
Publisher: American Society of Civil Engineers
Source: Journal of construction engineering and management, 2009, v. 135, no. 6, p. 448-457 How to cite?
Journal: Journal of construction engineering and management 
Abstract: This research resorted to the use of construction operations simulation modeling to investigate the cost efficiency of waste-handling practices on the Kai Tak Airport demolition project in Hong Kong. By modeling the site operation of sieving and stockpiling broken concrete, the well-established construction simulation methodology of CYCLONE was contrasted with the newly developed simplified discrete event simulation approach (SDESA). Further, the SDESA model was readily extended to include (1) raw demolition waste collecting and sorting; (2) broken concrete sieving and stockpiling; (3) steel bar recycling; and (4) debris disposal at the landfill. The production rate derived from simulation was indicative of a close match between the simulation model and the actual site system. The resulting simulation model provided a basis for evaluating the cost efficiency of actual site operations and alternative resource provision scenarios being postulated. Through computer simulation, the actual site operation was found smooth and efficient with utilization rates for resources of different types ranging from 79 to 99%. In addition, the cost-time reduction ratios were calculated for four alternatives of resource provisions in comparison with the original base case. The research findings suggested that provided the project budget had satisfied the higher cash flow requirement, doubling the resource provision on site would potentially cut the project duration by half and not increase the total direct cost.
URI: http://hdl.handle.net/10397/31239
ISSN: 0733-9364
EISSN: 1943-7862
DOI: 10.1061/(ASCE)0733-9364(2009)135:6(448)
Appears in Collections:Journal/Magazine Article

Access
View full-text via PolyU eLinks SFX Query
Show full item record

SCOPUSTM   
Citations

5
Last Week
0
Last month
0
Citations as of Sep 11, 2017

WEB OF SCIENCETM
Citations

4
Last Week
0
Last month
0
Citations as of Sep 21, 2017

Page view(s)

53
Last Week
2
Last month
Checked on Sep 17, 2017

Google ScholarTM

Check

Altmetric



Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.